Right-of-Way Permits

A Right-of-Way Permit is required for any work in the City’s right-of-way. 

Application Process

  1. Create an account and apply online at West Valley City’s Permitting and Licensing Portal
  2. Upload required submittals.
  3. As outlined in Chapter 1-2 of the West Valley City Municipal Code, construction activities that damage newly paved roads will be assessed an additional Asphalt Pavement Age-Based Damage Fee. Applicable locations for the additional fee can be found on the Asphalt Age Map.
  4. Once the right-of-way permit application is completed correctly and all required submittals are included, it will be submitted to the appropriate person for review. Notification will be given of the approval or denial within seven business days. A pre-construction meeting will be required.     

Required Submittals

The following items 1 to 3 must be on file with the Engineering Division prior to the acceptance of an excavation permit application. The remaining items are either optional or required depending upon the specifics associated with the excavation permit.

  1. Current copy of a Utah Contractors License.
  2. An original Certificate of Insurance with West Valley City listed as the certificate holder (Each Occurrence $1,000,000 minimum, General Aggregate $1,000,000).
  3. An original License and Permit Bond bound to West Valley City for a minimum of $10,000 (sufficient to cover all work done for a period of 12 months). Bond Continuation Certificates may be required.

    Note: We do not supply the forms for items 2 and 3; they are obtained from your insurance carrier / bonding company (original copies only; no faxes). If you are sending these documents to us, please send them to the following address:

    Attention: Ryan Ramirez
    West Valley City Engineering Division
    3600 S Constitution Boulevard
    West Valley City, UT 84119

  4. MUTCD compliant traffic control plan for all work within the roadway (samples available upon request).
  5. Materials submittals required.
  6. Street closures will require at least seven days advance notice along with a certified traffic control plan prior to approving the road closure request. This permit is obtained from our office and must be approved by the City Engineer, Police Department and Fire Department.

Inspection Requirements (after permit approval only)

An inspection time must be scheduled at least 24 hours prior to beginning any construction (48-hour notice required for all weekend work). Call 801-963-3318 to schedule an inspection.

Construction

See West Valley City Engineering Standards.

For Assistance or Questions

Permits

Ryan Ramirez
Permits Officer
Phone: 801-965-5842
Email Ryan Ramirez

For an inspection or to activate a permit please call 801-963-3318.